As Chris says the builder was never going to cut and seal the track, we had one guy in mind to do it but he never got back to us do we presumed after several calls and emails he didn't want the job. We have however found the company that's sealed the track last time and they also have the same astro from last time so hopefully enough to cover the right hand side of the track. He is supposed to be coming down tomorrow to have a look and come up with a price. The only thing is he won't be free to do it for 2-3 weeks so in the mean time we need to sort out all the other jobs I.e finish off cementing the table top walls so they're smooth, then painting them. Also fixing down a permenant track barrier between the straight near the rostrum and the walkway next to the rostrum.