Update 22.5.12
 
Ok folks

After a hastily arranged meeting with Lianne at the track this afternoon, I have some good news to report to our members.

And after berating the council that the originally proposed parking area offered was inadequate, they have finally acknowledged that its building would be wasteful, given our imminent application to extend past it! so

They have agreed to provide our expanding club, with a considerable parking area that extends towards the new gymnastics building and down to the middle of the two cabins. :woot: The area will have basic, but adequate surfacing and will have the knee high wooden fence, down and across, preventing anyone driving onto the football pitches right up to our cabins. (save for a small access). The yet to be seeded area left over toward the new building, will be available to pitch on next year. :woot:

The works will be done immediately and are expected to be finished within 2 weeks. :thumbsup:

I will still be submitting the previously mentioned funding application to the council, which ultimately aspires to the building of a purpose built rostrum and club house.

Will keep you posted. ;)

Darren
Chairman
BMRCC

Big Show 22-05-2012 09:26 PM

parking
 
Well done Darren, all your meetings and paitance has paid off for the club.
Well done.

Cr3Ad 22-05-2012 10:03 PM

this is good news, just the thing to boost the club in a new direction cheers :-)

budfish 22-05-2012 10:22 PM

Quote:

Originally Posted by Dwales1 (Post 657523)
Ok folks

After a hastily arranged meeting with Lianne at the track this afternoon, I have some good news to report to our members.

And after berating the council that the originally proposed parking area offered was inadequate, they have finally acknowledged that its building would be wasteful, given our imminent application to extend past it! so

They have agreed to provide our expanding club, with a considerable parking area that extends towards the new gymnastics building and down to the middle of the two cabins. :woot: The area will have basic, but adequate surfacing and will have the knee high wooden fence, down and across, preventing anyone driving onto the football pitches right up to our cabins. (save for a small access). The yet to be seeded area left over toward the new building, will be available to pitch on next year. :woot:

The works will be done immediately and are expected to be finished within 2 weeks. :thumbsup:

I will still be submitting the previously mentioned funding application to the council, which ultimately aspires to the building of a purpose built rostrum and club house.

Will keep you posted. ;)

Darren
Chairman
BMRCC

Well done mate you might be a rubbish driver but at least you're on the council like a crack head with £50 in his pocket

Darren Wales 23-05-2012 05:20 PM

Quote:

Originally Posted by budfish (Post 657612)
Well done mate you might be a rubbish driver but at least you're on the council like a crack head with £50 in his pocket

Lol :lol:

Darren Wales 09-07-2012 03:38 PM

Further update
 
All,

Unfortunately the surfacing of the newly sectioned off parking area has not been completed as promised by the council as per my last update.

I have chased them once again today and they have replied as follows

"At present I cannot provide you with an update. I have been told I
cannot proceed with the works until our Highways section provides their
costs - this is what I am waiting for. I have chased them this afternoon
again...

Sorry for the delay - As and when I get permission to start I will let
you know, until then please bear with me."

Regards
Kevin Dickinson
Building + Facilities Officer


I have made it clear to both Kevin and Lianne that the delay in completing this work is impacting on meetings, especially with the current weather and they assure me they will complete the works as a priority.

I have also had confirmation from Lianne, that following receipt of the clubs wishes, she has submitted an application for an extension to be built on the rear of the current football club house, which will contain toilet and changing facilities for the exclusive use of both our club and the cycle speedway. It is hoped this application will be approved and started this year but further confirmation will follow.

For now

Darren
Chairman
BMRCC

budfish 09-07-2012 03:54 PM

Good work Darren :thumbsup:

Kevin might need water boarding to help him come to a quick conclusion ?????

Buds

Big Show 09-07-2012 09:15 PM

Nice work Darren. Its good that the club has someone like you to voice the clubs needs.

Darren Wales 25-09-2012 04:55 PM

Facilities Update
 
As most may know we (ourselves and the Cycle Speedway club) have joined forces to sort what should be basic facilities, that we had before the track relocation.

Whilst we do have access to the gym toilets, we are now looking to secure our own toilets with changing facilities and have agreed with the council and Bury Juniors, to use half of the ground floor of the football clubhouse.

Plans have been drawn with the council and we are currently in the process (myself and the speedway Chairman) of submitting an application for funding for the costs of refurbishment. The club have spent a fair bit of monies on expenditure since the track relocation and of course we are not prepared to spend further on returning previously supplied facilities. That said, we will be getting much better facilities. As I have previously stated, the council accept that they should return these to us but they have no funds instead they are supporting us in the funding bid. The bid will include electricity to the cabins and it is hoped to be approved before the end of this year and works completed by April 2013. (fingers crossed)

I have also made a tentative approach to the planning dept with regards to the possibility of a purpose built clubhouse and rostrum. Of course this is not an urgent need but a future plan. More will be discussed at the AGM next Thursday.

I have been asked to provide a proposed plan of what we would look to build, to the planning office for them to advise me on whether it would be approved.
Can anyone assist with this? Please get in touch asap.


My vision In brief, the ground floor would be essentially storage, but contain internal stairs to the first floor viewing area and race control. We should look at the possibility of ramp access to the front for wheelchairs. The building would be secured by steel doors/shutters and the viewing area would need to secure from local youths etc so possibly shutters again.
I guess brick built. The current cabin location seems to be the only real option and as the new gym is in the background, i'm hoping will not raise objections from locals etc.

See you all at the AGM Thursday 4th October 2012 7.30pm.

Darren Wales
Chairman
BMRCC

Howler 26-09-2012 08:09 PM

Councils move slowly, but sounds like we're making progress eventually. Good work Darren.

johnnygibbon 27-09-2012 06:53 AM

Awsome
 
Good work Darren burys coming


All times are GMT. The time now is 06:14 AM.

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2025, vBulletin Solutions, Inc.
oOple.com